Explanation:
B is correct because Project Management is one of the SAP Activate workstreams. The Project Management workstream covers all the activities related to planning, executing, monitoring, controlling, and closing the project. It includes tasks such as defining project scope, schedule, budget, resources, risks, issues, quality, communication, and stakeholder management.
D is correct because Data Migration is one of the SAP Activate workstreams. The Data Migration workstream covers all the activities related to preparing, extracting, transforming, validating, and loading data from legacy systems to SAP systems. It includes tasks such as defining data migration strategy, scope, approach, tools, roles, responsibilities, quality criteria, and testing scenarios.
Verified Reference: SAP Activate Methodology Workstreams Names update