Question#1

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due.
What should the CM do in this situation?

A. Put the contractor's unopened bid in tight security until the bid opening has been completed.
B. Send the bid back to the contractor and apologize for the mishap.
C. Include the unopened bid. since it clearly was an oversight.
D. Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Explanation:
According to the CMAA Construction Management Standards of Practice (SOP), Chapter 6 C Contract Administration, the Construction Manager is responsible for ensuring that all bid procedures are handled in strict accordance with the procurement requirements and instructions to bidders.
CMAA guidance emphasizes:
“In the event of irregularities during the bidding or proposal submission process, the Construction Manager must immediately notify the Owner and refer to the procurement documents for direction before taking any independent action.”
The CM must maintain impartiality, protect the integrity of the bidding process, and avoid unilateral decisions that could imply bias or alter bid fairness. Since the bid in question was timestamped incorrectly, the proper step is to inform the Owner and review the bidding instructions to determine the correct procedural resolution.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, Chapter 6 C Contract Administration, Section:
“Procurement and Bidding Procedures,” pp. 61C64.
CMAA CM Study Guide, Contract Administration Domain, Objective 6.1: “Ensure fairness, transparency, and compliance in the bid process.”

Question#2

= P×[(C+T+Q)+3] P is Probability
C is Cost T is Time Q is Quality
This equation best describes a(n)

A. overall risk score.
B. cost time quality evaluation.
C. risk variable score.
D. Monte Carlo simulation equation.

Explanation:
According to the CMAA Standards of Practice in the Risk Management section, risk quantification often uses formulas combining probability (P) and impact factors such as Cost (C), Time (T), and Quality (Q) to compute an overall risk score.
The CMAA explains:
“Risk scoring combines the likelihood (probability) of occurrence with the magnitude of its potential impact across cost, time, and quality metrics. The resultant value represents the overall risk score used for prioritization in the risk register.”
The given formula aligns directly with that concept ― it mathematically expresses a weighted overall risk score, not a simulation or isolated variable measure. A Monte Carlo simulation is a separate probabilistic modeling technique, not a single-score formula.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 9 C Risk Management, Section: “Risk Identification and Quantification,” pp. 85C87.
CMAA Study Guide, Risk Management Domain, Objective 9.3.

Question#3

The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non-conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material .
In this scenario, which of the following options represents the BEST course of action?

A. Based on the engineer of record's recommendation, the contractor should develop a repair detail and submit for approval.
B. The concrete should be chopped out, rebar dowels should be drilled into the new slab, and the repair detail should be implemented.
C. The agency should accept as-is and rely on the primary system.
D. All slab concrete should be removed.

Explanation:
Per CMAA Standards of Practice (Chapter 5 C Quality Management and Chapter 6 C Contract Administration), when non-conforming work is discovered and the contractor fails to comply with approved corrective instructions, the appropriate procedure is for the contractor to submit a proposed corrective action or repair detail for review and approval by the engineer of record and the owner.
The SOP emphasizes:
“The contractor is responsible for proposing a corrective action for nonconforming work. The CM shall ensure the proposal is reviewed and approved by the design professional and owner prior to implementation.”
Accepting the condition as-is (Option C) would be improper without formal approval, and unilateral removal or demolition (Options B or D) should only occur after the approved corrective process is completed.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 C Quality Management, Section “Nonconforming Work and Corrective Action.”
CMAA CM Study Guide, Quality Management Domain, Objective 5.4: “Coordinate the review and approval of corrective actions for nonconforming work.”

Question#4

Lifecycle analysis of a project will provide the greatest impact during which of the following phases?

A. Pre-Design
B. Design
C. Construction
D. Procurement

Explanation:
According to the CMAA Standards of Practice, lifecycle analysis (LCA) is most effective when applied early in project planning―specifically during the Pre-Design phase―because the ability to influence materials selection, building systems, and operational efficiency is at its highest before design decisions are finalized.
The CMAA defines lifecycle analysis as:
“An evaluation of the total cost and performance of a facility over its useful life. Lifecycle assessment is most effective when conducted during the Pre-Design phase, where project alternatives can be compared, and design direction can be influenced.”
During later phases, such as design or construction, changes have diminishing cost-benefit potential. Therefore, the Pre-Design phase is where lifecycle analysis yields the greatest impact on sustainability, cost, and performance outcomes.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 8 C Sustainability and Environmental Stewardship, Section: “Lifecycle Costing,” pp. 78C80.
CMAA CM Study Guide, Sustainability Domain, Objective 8.1.

Question#5

The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on.
What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?

A. Market conditions should not be a factor in when a project is advertised.
B. Postpone advertising for one year.
C. Advertise the project and award to lowest bidder.
D. Consider the impacts of current market conditions and revise project strategy.

Explanation:
CMAA encourages the CM and owner to respond adaptively to changing conditions in the market rather than rigidly follow plans that become unrealistic. The owner and CM should continuously monitor external factors, such as contractor availability, market pricing escalation, and risk, and adapt the procurement and strategy accordingly. In a wildly different market, proceeding blindly (as in A or C) could lead to failed bids or cost overruns. Postponement (option B) may be an option, but doing so for a fixed period (one year) is inflexible and risky. The prudent option, consistent with CMAA’s advocacy for adaptable project management and risk mitigation, is to consider the impacts of current market conditions and revise the project strategy.

Disclaimer

This page is for educational and exam preparation reference only. It is not affiliated with CMAA, Certified Construction Manager, or the official exam provider. Candidates should refer to official documentation and training for authoritative information.

Exam Code: Construction ManagerQ & A:  65  Q&As Updated:  2026-11-21

  Get All Construction Manager Q&As