L4M3 Online Practice Questions

Home / CIPS / L4M3

Latest L4M3 Exam Practice Questions

The practice questions for L4M3 exam was last updated on 2025-09-15 .

Viewing page 1 out of 14 pages.

Viewing questions 1 out of 71 questions.

Question#1

Which of the following is the reason why liquidated damage clauses are embedded into a contract?

A. Because liquidated damages are the only remedy
B. To penalise the supplier for their wrongdoing
C. To avoid argument on correct measure of damage
D. Because compensation will be awarded immediately

Explanation:
Liquidated damages are an amount of money, agreed upon by the parties at the time of the contract signing, that establishes the damages that can be recovered in the event a party breaches the contract. The amount is supposed to reflect the best estimate of actual damages when the parties sign the contract. These usually apply to a specific type of breach, and in construction, it is frequently the failure to complete work on time. Liquidated damages clauses are usually written as some sort of formula, for example:
Total Contract Price C [(X amount of $ per day) x (number of days late)]
Including a liquidated damages clause can provide many benefits, the most important of which is predictability. When setting a predetermined amount of damages, it allows both parties a chance to negotiate and settle on a number they both feel is fair and reasonable. From the owner’s perspective, this acts like a cheap form of insurance against your contractors. In the event of a breach, the owner can immediately calculate the damages without going through the trouble of proving actual damages. Proving actual damages can be a complicated, lengthy, and costly process.
From a contractor perspective, this allows them to analyze the level of risk involved, and schedule appropriately. It also allows them the opportunity to limit the damage claims of the owner.
Reference:
- Construction Contract Clauses: What Is a Liquidated Damages Clause?
- CIPS study guide page 158-159
LO 3, AC 3.2

Question#2

Bandpro is a reseller of branded computer products to the private and public sector. The procurement team must purchase 500 items each day solely by multiple phone calls and emails to suppliers. Due to this practice, it takes a lot of time to track and collect relevant documents. Some important documents even get lost, which makes procurement audit more burdensome.
Which of the following would increase the robustness of audit trails in procurement activities?

A. Every evidence must be recorded by paper
B. Adopt e-procurement
C. Spend less time on auditing procurement procedures
D. Rectify non-compliant activities

Explanation:
Audit trail is a chronological record the sequence of events connected to a given transaction, such as a purchase of raw materials, payroll disbursements, or a detailed financial statement. The record includes all the source documents connected to the transaction, providing context and clarity in the event a review is required. The more comprehensive the documentation, the more effective the audit trail is when used to create financial reports, verify information, and ensure compliance while eliminating fraud.
In the scenario, the procurement team gets the quotation from phone calls and emails which have weak audit trails and lack of transparency. One solution may be increasing the use of e-procurement system.
Reference:
- What is an audit trail?
- CIPS study guide page 6-7 LO 1, AC 1.1

Question#3

A company needs to source a product from oversea. It wants to overcome technical barrier to cross-border trade by using standards in the specification.
Which of the following is most likely to be incorporated into that specification?

A. National standards
B. Company standards
C. Brands
D. International standards

Explanation:
Exporting enterprises must sometimes incur additional costs as they adapt their production to the changing legal requirements of the recipient country. Such requirements can thus create technical barriers to trade. Discrepancies between product rules adopted by different countries can involve numerous aspects: weight, size, packaging, ingredients, mandatory labeling, shelf-life conditions, testing and certification procedures etc.
One way to overcome these barriers is to adopt international standards. Overseas companies may be more familiar with international standards without looking at specific regulations of importing countries.
Reference:
- What is a technical barrier to trade?
- CIPS study guide page 88-89
LO 2, AC 2.1

Question#4

In which of the following conditions, request for quotation produces the best results?

A. With an ambiguous specification
B. Under framework agreements
C. Under a complex process
D. With strategic items

Explanation:
Request for quotation has valuable function when its use is properly controlled. It works the best under framework agreements where the contract terms are already fixed.
Reference: CIPS study guide page 3
LO 1, AC 1.1

Question#5

A construction company often subcontracts approximately 50% of the project works because of unpredictable customer's demand. Although larger corporate customers require quick response to RFQ, the time lapse between tender bid submission and contract commencement is usually long.
Which of the following arrangement would benefit both the contractor and customer?

A. Collateral contract
B. Bilateral contract
C. Indemnity agreement
D. Framework agreement

Explanation:
According to the scenario, customers' demand changes regularly but the construction project commencement often delays. If the contractor and the customer mutually sign a legally binding contract too soon long before the commencement, the contractor may suffer poor cash flow (it must buy the materials first but has to wait for long time to be paid). A framework agreement may help both parties.
A framework agreement is a formal agreement between two organisations that is intended to become legally binding in the event that a contract is created.
A framework agreement could benefit the both parties in the following ways:
- At the time of signing, the framework agreement has not yet become a legally binding contract. The contractor and client only agree on the principles of future contracts (such as whether the work can be subcontracted or how payment will be proceeded). A well structured framework agreement will allow both parties to apply changes before contract commencement, especially regarding price and quality.
- The framework agreement assures a certainty between the contractor and client.
- The administrative works is reduced under a framework agreement.
Reference:
- CIPS study guide page 60-62
- Framework Agreements: Practice and Pitfalls LO 1, AC 1.3

Exam Code: L4M3Q & A: 190 Q&AsUpdated:  2025-09-15

 Get All L4M3 Q&As