PMI-RMP Online Practice Questions

Home / PMI / PMI-RMP

Latest PMI-RMP Exam Practice Questions

The practice questions for PMI-RMP exam was last updated on 2025-06-03 .

Viewing page 1 out of 12 pages.

Viewing questions 1 out of 64 questions.

Question#1

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges.
What two actions should the risk owner take? (Choose two.)

A. Implement the secondary risk response and update the project documents.
B. Conduct meeting with all stakeholder to agree on post impact solutions.
C. Set the corresponding trigger conditions to the secondary risk.
D. Engage the project manager to authorize the secondary risk's response.
E. Update and communicate assessments of the secondary risk's impact.

Explanation:
The risk owner should implement the secondary risk response, as it is now being tolerated, and update the project documents accordingly. They should also update and communicate the assessments of the secondary risk's impact to ensure everyone is aware of the situation.
According to the PMI-RMP Handbook1, the risk owner is responsible for implementing the risk response plan and monitoring the risk and its secondary risks.
Therefore, the risk owner should take the following two actions when the secondary risk emerges:
Implement the secondary risk response and update the project documents. This action is consistent with the risk response strategy of tolerance, which means accepting the risk and its consequences. The risk owner should execute the planned response for the secondary risk, such as contingency plans or fallback plans, and update the relevant project documents, such as the risk register, the risk report, and the lessons learned register, to reflect the current status and impact of the risk.
Update and communicate assessments of the secondary risk’s impact. This action is consistent with the risk monitoring and control process, which involves tracking the identified risks, evaluating their impact and probability, and reporting the risk information to the appropriate stakeholders. The risk owner should reassess the secondary risk’s impact on the project objectives, such as scope, schedule, cost, and quality, and communicate the results to the project manager and other relevant stakeholders, such as the sponsor, the customer, and the team members.
Reference: PMI-RMP Handbook1
PMBOK Guide, 6th edition, Chapter 11: Project Risk Management2

Question#2

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence .
Which technique should the risk manager use?

A. Political, economic, social, technological, legal, and environmental (PESTLE) analysis
B. Strengths, weaknesses, opportunities, and threats (SWOT) analysis
C. Decision tree analysis
D. Cost-benefit analysis

Question#3

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?

A. Add buffers to the schedule to accommodate risk.
B. Ensure the risk register includes all identified risks.
C. Discuss the risk response strategies with the stakeholders.
D. Develop a communication plan to share updates on risks.

Explanation:
The project manager should discuss the risk response strategies with the stakeholders to handle their expectations. This will help the project manager to align the risk responses with the stakeholder’s risk appetite, preferences, and expectations. It will also help the project manager to obtain the stakeholder’s support and approval for the risk responses. This is the best way to ensure clear visibility on the project risks and progress. Adding buffers to the schedule to accommodate risk (option A) is not a good practice, as it may create false expectations and hide the true impact of risk. Ensuring the risk register includes all identified risks (option B) is important, but it is not enough to handle stakeholder expectations. The project manager also needs to communicate the risk register to the stakeholders and discuss the risk responses with them. Developing a communication plan to share updates on risks (option D) is also a good practice, but it is not sufficient to handle stakeholder expectations. The project manager also needs to involve the stakeholders in the risk response planning process and obtain their feedback and approval.
Reference: PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 97; PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 6th ed., 2017, p. 407.
The project manager should develop a communication plan to share updates on risks (D) to handle stakeholder expectations, especially since the organization has a low risk appetite and stakeholders are very engaged. This approach ensures that stakeholders are regularly informed about the project's risks and progress, addressing their concerns and expectations. This is supported by the PMI's PMBOK Guide, Sixth Edition.

Question#4

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings .
How will this help improve the project's risk management activities? (Choose 3)

A. By helping to monitor variances and trends frequently throughout the project
B. By helping to determine the overall project risks
C. By helping the lessons learned from previous risks to be efficiently utilized
D. By helping to update the project scope statement document
E. By helping update the risk register and close out expired risks

Question#5

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.
What should the project manager have done differently?

A. Executed the risk strategy response and recorded it in the risk register.
B. Performed an analysis to affirm the request is valid before submitting.
C. Informed the client and the project sponsor that the request is being submitted.
D. Contacted the other stakeholders so they know the request is in process.

Explanation:
The project manager should have performed an analysis to ensure that the change request was valid and well-supported before submitting it to the sponsor. This would help in making a strong case for the change request and increase the chances of its approval.
The project manager should have performed an analysis to affirm the request is valid before submitting, as this would help to justify the need for the change and to demonstrate its impact on the project objectives, scope, schedule, cost, quality, and risk. The project manager should also have consulted with the project team, the subcontractor, and the risk owner to determine the best risk response strategy and to estimate the resources and time required for the change. By performing an analysis, the project manager could have increased the chances of getting the change request approved by the sponsor and avoided wasting time and effort on an invalid request.
Reference: The Standard for Risk Management in Portfolios, Programs, and Projects, page 79; PMBOK Guide, 6th edition, page 115.

Exam Code: PMI-RMPQ & A: 203 Q&AsUpdated:  2025-06-03

 Get All PMI-RMP Q&As