PMI-RMP Online Practice Questions

Home / PMI / PMI-RMP

Latest PMI-RMP Exam Practice Questions

The practice questions for PMI-RMP exam was last updated on 2026-04-10 .

Viewing page 1 out of 8 pages.

Viewing questions 1 out of 40 questions.

Question#1

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.
How should the risk manager address this concern?

A. Risks are documented to the practicable extent possible.
B. Probability of the risk was very low. so the risk was not documented.
C. Impact of the risk was assessed to be insignificant, so the risk was not documented.
D. A similar risk never occurred in the past, so it was not considered.

Explanation:
In risk management, it is standard practice to document risks to the extent that they are identifiable and reasonably foreseeable. If an undocumented risk is realized, the risk manager should address the concern by explaining that risks are documented to the practicable extent possible. This means that while every effort is made to identify and document risks, some risks may not be captured due to their low probability, lack of historical precedence, or other factors.
PMI’s guidelines on risk management recognize that not all risks can be foreseen and documented, and risk management processes should focus on those risks that are most likely to impact the project.

Question#2

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?

A. Avoid the risk
B. Transfer the risk
C. Ignore the risk
D. Accept the risk

Explanation:
Since the project manager cannot avoid, transfer, or mitigate the risk, the only remaining option is to accept the risk and develop a contingency plan to handle it if it occurs.
According to the PMI-RMP Exam Content Outline1, one of the tools and techniques for risk response planning is risk response strategies. These are the actions that the project manager and the project team take to address the identified risks, either positive or negative. For negative risks or threats, the PMI-RMP Exam Content Outline1 lists four possible strategies: avoid, transfer, mitigate, and accept. Avoid risk means changing the project plan to eliminate the threat or its impact2. For example, changing the scope, schedule, or budget to avoid a risk.
Transfer risk means shifting the impact of a threat to a third party, such as a contractor, vendor, or insurer2. For example, buying insurance, outsourcing, or using performance bonds to transfer a risk. Mitigate risk means reducing the probability and/or impact of a threat2. For example, conducting more tests, adopting best practices, or providing training to mitigate a risk.
Accept risk means acknowledging the existence of a threat and being willing to deal with its consequences2. For example, doing nothing, establishing a contingency reserve, or developing a contingency plan to accept a risk.
In this question, the project manager has determined that they cannot outsource work (transfer) nor eliminate the scope (avoid). They also discover that they cannot buy insurance (transfer) or mitigate the risk. Therefore, the only remaining option is to accept the risk. Accepting the risk does not mean ignoring the risk, but rather recognizing it and preparing for its potential occurrence and impact. Therefore, the best answer is D.
Reference: 1: PMI-RMP Exam Content Outline, page 9. 2: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) C Sixth Edition, page 443.

Question#3

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?

A. Put the risk on the watch list.
B. Seek guidance from subject matter experts (SMEs).
C. Ignore this risk as it is not critical.
D. Inform the stakeholders about this risk.

Explanation:
Since the probability and impact the risk are both low, it is appropriate to put the risk on the watch list. This allows the risk manager to monitor the risk without expending significant resources on it. A watch list is a list of low-priority risks that are not actively managed, but are monitored for changes. A watch list can help the risk manager to keep track of the risks that have low probability and low impact, and to reassess them periodically. Putting the risk on the watch list is the most appropriate action for the risk manager, as it allows him or her to document the risk and review it later. Seeking guidance from SMEs, ignoring the risk, or informing the stakeholders are not necessary actions for a low-priority risk, as they would consume time and resources that could be better spent on more critical risks.
Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 10; A Guide to the Project Management Body of Knowledge (PMBOK® Guide) C Sixth Edition, page 406.

Question#4

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.
What should the risk manager do?

A. Import a risk register from other industry chemical laboratories.
B. Define chemical laboratory safety risk thresholds.
C. Review published operational experience reports.
D. Draft threat and opportunity risks that come to mind.

Explanation:
Reviewing published operational experience reports from similar projects or industries can help the risk manager objectively identify risks for the chemical laboratory project. These reports provide valuable insights into potential risks and lessons learned from other projects.
According to the PMBOK Guide, one of the tools and techniques for the identify risks process is data gathering. Data gathering is the process of collecting information from various sources to identify potential risks that may affect the project objectives. One of the data gathering techniques is document analysis, which involves reviewing and analyzing available project documents and other information sources to identify potential risks. Some of the documents that can be analyzed are project charter, project management plan, stakeholder register, assumptions log, agreements, and lessons learned1.
One of the information sources that can be useful for identifying risks in a project constructing a chemical laboratory is published operational experience reports. These are reports that document the experiences, lessons learned, best practices, and recommendations from other organizations or projects that have constructed or operated chemical laboratories. These reports can provide valuable insights into the common risks, challenges, and opportunities that are associated with chemical laboratory projects, such as safety hazards, environmental regulations, equipment failures, design specifications, quality standards, and stakeholder expectations. By reviewing published operational experience reports, the risk manager can objectively identify risks that are relevant and applicable to their project, as well as learn from the successes and failures of others23.
Some of the other options are not relevant or appropriate for the question scenario:
Importing a risk register from other industry chemical laboratories is not a valid option, as it would not allow the risk manager to objectively identify risks that are specific and unique to their project. A risk register is a document that records the identified risks, their causes, impacts, responses, owners, and other information related to the risk management process. A risk register is a project-specific document that reflects the characteristics, objectives, and context of a particular project. Importing a risk register from other industry chemical laboratories would not ensure that the risks are relevant, accurate, or comprehensive for the risk manager’s project. Moreover, it would violate the intellectual property rights and confidentiality agreements of the other projects1.
Defining chemical laboratory safety risk thresholds is not a tool or technique for identifying risks, but rather for performing qualitative risk analysis. Risk thresholds are the measures of the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Risk thresholds are used to determine the significance of each risk and to prioritize them for further analysis or action. Defining chemical laboratory safety risk thresholds would not help the risk manager to objectively identify risks, but rather to evaluate them1.
Drafting threat and opportunity risks that come to mind is not an objective or systematic way of identifying risks, but rather a subjective and intuitive one. This option would rely on the risk manager’s personal judgment, experience, or creativity, which may not be sufficient or reliable for identifying risks in a project constructing a chemical laboratory. This option would also not ensure that the risks are based on factual and verifiable information sources, such as project documents or published reports. Drafting threat and opportunity risks that come to mind would not help the risk manager to objectively identify risks, but rather to generate them1.
: PMBOK Guide, 6th edition, pages 397-399, 414-415, 431-432, 441-4421; Risk Management Professional (PMI-RMP)® Cert Guide, pages 63-642; Risk Management Professional Exam Outline, page 73.

Question#5

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.
What should the risk manager do next?

A. Meet with the project team to brainstorm potential solutions to the problem.
B. Implement the risk response plan to remedy the problem as soon as possible.
C. Initiate discussions with the project manager to decide how to manage the problem.
D. Escalate the problem to the project sponsor to agree on the best course of action.

Explanation:
When a risk has materialized and become an issue despite preventive actions, the next logical step is to implement the pre-established risk response plan. This plan is designed specifically to address the risk if it occurs, ensuring that the project can quickly and effectively manage the issue. According to PMI's risk management guidelines, implementing the risk response plan is a critical step once a risk has been triggered, as it provides a structured approach to resolving the issue with minimal impact on the project.

Disclaimer

This page is for educational and exam preparation reference only. It is not affiliated with PMI, PMI Risk Management Professional, or the official exam provider. Candidates should refer to official documentation and training for authoritative information.

Exam Code: PMI-RMPQ & A: 278 Q&AsUpdated:  2026-04-10

  Get All PMI-RMP Q&As