PMP Exam Questions 2026 – Practice Test with Answers

Home / PMI / PMP

Latest PMP Exam Practice Questions

The practice questions for PMP exam was last updated on 2026-11-22 .

Viewing page 1 out of 2 pages.

Viewing questions 1 out of 10 questions.

Question#1

A project is approaching the closure phase. The project manager realizes that the team has consumed more hours than what was budgeted because some nonfunctional security requirements were not considered during project initiation.
What should the project manager do to avoid this issue in the future?

A. Conduct a mandatory security awareness program for all project team members.
B. Hold a retrospective on why the requirements were overlooked and update organizational process assets.
C. Change the status in the risk register to issue and activate the response plan.
D. Meet with team members of the security department and require the department to be involved from the project’s start.

Explanation:
The correct answer is B because the scenario requires disciplined compliance and quality governance rather than an immediate, informal, or purely administrative reaction. The selected response ― B. Hold a retrospective on why the requirements were overlooked and update organizational process assets. ― directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to verify mandatory requirements, analyze impact, and prevent uncontrolled delivery decisions that could create audit or acceptance exposure. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: process, compliance and quality governance, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Question#2

There are considerable differences in experience levels among project team members working on a project. Multiple stakeholders are requesting that deliverables relevant to them be assigned to the most experienced team members, which is not feasible.
What should the project manager do?

A. Request additional experienced team members be assigned to the project and adjust the resource management plan.
B. Inform stakeholders that the team members have been assigned and are capable of completing the tasks.
C. Assign the activities from the beginning of the project to the less experienced team members to meet the timeline.
D. Create a team agreement so that experienced team members mentor the less experienced members throughout the project.

Explanation:
The correct answer is D because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response ― D. Create a team agreement so that experienced team members mentor the less experienced members throughout the project. ― directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: people, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Question#3

A project team is tasked with implementing a new technology system for the end users. The project team currently lacks information on what the system is used for and how the end users would use it.
What should the project manager do?

A. Request the project management office (PMO) if they can support with beneficial information.
B. Hire external expert resources who have the knowledge about the system.
C. Encourage the senior project resources to find out the purpose of the system.
D. Ask the sponsor to define the project objectives and goals in the project documents.

Explanation:
The correct answer is D because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response ― D. Ask the sponsor to define the project objectives and goals in the project documents. ― directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: business environment, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Question#4

A project manager is leading an iterative project to develop a very innovative product. However, a group of stakeholders are hesitant because the high complexity of the product involves many business rules.
What should the project manager do?

A. Seek advice from other project managers within the company and review their methods to build credibility.
B. Meet with the project team to devise a plan to build credibility.
C. Present another iterative project that has been completed by the project team recently to build credibility.
D. Ensure that project iterations deliver early wins to build credibility.

Explanation:
The correct answer is D because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response ― D. Ensure that project iterations deliver early wins to build credibility. ― directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: people, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Question#5

A project lead is working on a large-scale, high-profile hardware development project for a new smartphone. The project sponsor has requested that a major priority feature almost fully developed be considered optional. At the same time, a new priority feature that has never been discussed is being added.
Which two actions should the project lead take? (Choose 2)

A. 3 Ask the project sponsor to add funds to the project budget for the extra work.
B. © Advise the product owner to deliver the original feature as a priority because it is almost completed.
C. Ensure the product owner reflects the change in the product backlog.
D. ) Ask the project sponsor to review the contract to check if there are penalties for this change . E . Continue to monitor the budget and project timeline and escalate issues to management as needed.

Explanation:
The correct answer is C, E because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response ― C. Ensure the product owner reflects the change in the product backlog.;
E. Continue to monitor the budget and project timeline and escalate issues to management as needed. ― directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: process, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Disclaimer

This page is for educational and exam preparation reference only. It is not affiliated with PMI, PMP Certification, or the official exam provider. Candidates should refer to official documentation and training for authoritative information.

Exam Code: PMPQ & A:  187  Q&As Updated:  2026-11-22

  Get All PMP Q&As