During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages.
Is this appropriate for a risk register, and why?
A. Yes, because the project registers should be tailored to meet the needs of the organization.
B. Yes, because risks are often identified as a result of issues being raised.
C. No, because an integrated project register should include the quality register as well.
D. No, because assumptions and dependencies are sources of risk.
Explanation:
Reference: http://prince2.wiki/Quality_Register_Template