A. To assign user stories to each team based on their capacity
B. To define the detailed architecture for the next PI
C. To align all Agile Release Train participants to a shared mission and common goal
D. To allow teams to finalize their backlogs
Explanation:
The SAFe POPM workbook defines PI Planning as “a cadence-based event that serves as the heartbeat of the ART,” aligning all teams on the ART to a shared mission and Vision. This makes the primary purpose of PI Planning alignment across ART participants around a common direction and goal.
5 0. During PI Planning, capacity allocation helps an ART to:
A. Increase team velocity by limiting dependencies
B. Balance new business features with enablers, tech debt, and maintenance
C. Prioritize only features with the highest WSJF score
D. Ensure that every team delivers the same number of stories each iteration
Answer: B
Explanation:
The SAFe POPM workbook states that capacity allocation helps balance functionality with Architectural Runway. It also shows allocation categories such as New Features, Enablers, and Tech Debt and Maintenance, and says teams agree on the percentage of capacity devoted to new Feature development versus Enablers, tech debt, and maintenance.