Question#1

Your purchasing department is interested in working with scheduling agreements.
What valid information can you share with them regarding release creation profiles? Note: There are 3 correct answers to this question.

A. A release creation profile triggers the creation of scheduling agreement schedule lines.
B. You can enter a release creation profile in a purchasing info record.
C. You can enter a release creation profile in the supplier master data.
D. A release creation profile controls the aggregation of schedule line quantities in a delivery schedule.
E. A release creation profile controls the periodicity of delivery schedule creation.

Question#2

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.

A. Planned order
B. Purchase order
C. Delivery schedule line
D. Purchase requisition

Question#3

You want to use split valuation for your refurbishing process to differentiate between materials based on the condition of the material.
What do you need to consider for the accounting data of your material?

A. For the valuation area, the price control must be standard price.
B. For each possible valuation type, the price control must be moving average price.
C. For each possible valuation type, the price control must be standard price.
D. For the valuation area, the price control must be moving average price.

Question#4

You test the various options that SAP S/4HANA offers for stock transfers between two different plants within the same company code.
Which of the following apply to stock transport orders? Note: There are 3 correct answers to this question.

A. You can post the goods issue from quality inspection stock in the supplying plant.
B. You can enter delivery costs in the stock transport order.
C. You can post the goods receipt to blocked stock in the receiving plant.
D. Two accounting documents are created at the time of goods issue posting - one for each plant.
E. The material on the road is managed as stock in transit in the receiving plant.

Question#5

For which of the following business scenarios does a situation template exist in Situation Handling? Note: There are 2 correct answers to this question.

A. The due date for a blocked invoice has passed.
B. A supplier confirmation is pending.
C. A contract is ready as a source of supply.
D. A purchase order approval is pending.